Date: July 2012

Our Rail Division was appointed by Colt Construction to carry out the installation of the felt roof works upon completion of an asbestos strip. Project Value - £30,000.00

Project Background

Everlast Group was appointed as a Tremco approved contractor to install the felt waterproofing on this existing relay room where works were delivered within a busy depot, meaning that the logistics of the project had to be managed with the Depot Manager on a daily basis.  

Client Benefits

Works included the roofing & scaffolding package minimising the number of sub-contractors on site.

  • Insurance backed 20 year material and workmanship Guarantee.
  • Regular meetings to review progress vs programme and address any detailing concerns.
  • Fortnightly inspections by the Tremco Technical representative to ensure waterproofing installed as per the specification.
  • Full comprehensive Operation & Maintenance file provided upon completion of works.
  • Project delivered on programme and to budget.